Tropicana Pipe Bridge

BLOG POST.

//Tropicana Pipe Bridge

Tropicana Pipe Bridge

Legeneering was approached by AngloGold Ashanti to fab a new pipe bridge for their Ball Mill project at the Tropicana Gold Mine in WA. We successfully secured the tender for the construction, fabrication, blasting, painting and testing of the pipe bridge portion of the mill.

3D rendering supplied by MACA

Pipe Bridge in the paint shop

Despite the high-pressure deadline, we delivered on time to the client with zero safety incidents over the seven-week project period.

“You’ve outshone everyone else” – client feedback

The pipe bridge is 33m long, 9m high and 3.5m wide and consisted of over 30 Tonne of structural steel. The bridge had a full abrasive blast and a three coat protective paint system. Legeneering additionally completed Dimensional Verification of each component via our unique processes to ensure a perfect fit onsite.

See a time-lapse video of the workshop during fabrication and construction below

Green pipe bridge

3D rendering supplied by MACA

More Posts

THE LATEST IN LEGENEERING NEWS

Tropicana Pipe Bridge

Legeneering was approached by Anglo Gold Ashanti to fab a new pipe bridge for their Ball Mill project at the Tropicana Gold Mine in WA. We successfully secured the tender for the construction, fabrication, blasting, painting and testing of the pipe bridge portion of the mill.

Submarine Cradle Success

In May, Legeneeing secured a contract to fabricate, blast and paint a Submarine cradle extension for BAE Systems Australia. A full abrasive blast and protective coating system were required to ensure the cradle would endure throughout its lifetime.

OUR CAPABILITIES

Connect With Us

Contact
2019-01-24T23:57:54+00:00